The following is an overview of work completed since March and expected in the next 30 days on the UW-Eau Claire Garfield Avenue redevelopment project:

image

Work completed since March 20 project launch

  • Installed temporary walkways at base of Garfield Avenue hill to reroute pedestrian traffic
  • Installed tree protection fencing
  • Installed construction fence and temporary lighting
  • Installed erosion control
  • Installed directional signage
  • Removed surface treatments (pavement, topsoil) along Garfield Avenue from base of hill to Ecumenical Religious Center
  • Completed first stage of construction of first two steam pits at bottom of hill; poured and formed concrete box conduit for steam lines between pits
  • Installed new water main for service to Schofield Hall, Old Library, McIntyre Library, Thomas Hall and Putnam Hall
  • Relocated chilled water main in McIntyre Library loading dock area to accommodate new steam distribution system

Work to be completed in next 30 days

  • Install steam and condensate piping between first two steam pits
  • Excavate and complete first stage of construction for third and fourth steam pits; pour and form concrete box conduit for steam lines between pits
  • Install sanitary sewer from Putnam Hall to Schofield Hall
  • Take old steam system offline and remove

Upcoming key date

  • Closure of campus footbridge as of May 22 for reconstruction of steam pit at south end

Photo cutline (top photo): This aerial view shows progress on installation of a new steam system along UW-Eau Claire's Garfield Avenue as part of the Garfield Avenue redevelopment project that began in March 2017 and is expected to be completed by fall 2018.

Photo cutline (photo in story): A view of work on the Garfield Avenue redevelopment project from the south end of the UW-Eau Claire footbridge.

 


Thanks for your interest in UW-Eau Claire. Let's get started!

Select a student category below for admission guidelines, important deadlines and instructions.

NOTE: To complete your application to UW-Eau Claire you will be taken off of this website to access the UW System online admission application.


If you want to apply for employment, please click here.

×