UW-Eau Claire construction update: June 1, 2018

The following is an overview of work completed since May 1, 2018, and expected in the next 30 days on UW-Eau Claire construction projects.

(The photo above shows the status of the Pablo Center at the Confluence in downtown Eau Claire. Progress on the project can be followed online.)

Work completed since May 1, 2018

Garfield Avenue redevelopment

(See live video stream of project — view from Schofield Hall.)

  • Partially completed irrigation installation.
  • Began tree planting in Putnam Park outdoor classroom area.
  • Installed concrete landscaping blocks in Blugold Mixer, amphitheater and outdoor classroom areas.
  • Began utilities removal and replacement between Hibbard Hall and Kjer/Brewer/Zorn complex (expected completion June 8).

Karlgaard Towers south tower renovation

  • Completed new student room window installations.
  • Started bathroom and lounge window installations on south side of tower.
  • Completed plumbing rough-ins.
  • Started plumbing fixture installations.
  • Completed rough electrical work in student rooms.
  • Installed most hallway lighting and smoke detectors.
  • Completed heating, ventilation and air-conditioning installation.
  • Completed painting in student rooms.
  • Started staining interior doors.
  • Completed painting penthouse exterior.
  • Continued installing rough electrical on floor 1.
  • Continued installing second of two new elevators.
  • Completed installation of steel studs.
  • Completed tile installation in bathrooms on floors 7, 6 and 5.
  • Completed drywall installation in common areas.
  • Installed first-floor windows.
  • Completed steel structure for new entryway addition.
  • Installed carpet in student rooms and hallways on floors 10 and 9.

New residence hall

(See live video streams of project — views from Karlgaard Towers, heating plant, Horan Hall.)

  • Completed installing block walls from basement through floor 1.
  • Completed installing footings on east side of structure.
  • Completed backfilling up to foundation walls.
  • Completed chilled water line and electrical installation.
  • Partially completed steam line installation.

Pablo Center at the Confluence

Work to be completed in next 30 days

Garfield Avenue redevelopment

  • Continue grading, irrigation installation and landscaping of project site.
  • Continue utilities removal and replacement between Hibbard Hall and Kjer/Brewer/Zorn complex (expected completion June 8).

Karlgaard Towers south tower renovation

  • Continue bathroom and lounge window installations on south side of tower.
  • Complete installation of hallway lighting and smoke detectors.
  • Continue plumbing fixture installations.
  • Install penthouse doors.
  • Continue installing rough electrical on floor 1.
  • Continue installing second of two new elevators.
  • Continue tile installation in bathrooms on floors 4, 3 and 2.
  • Continue steel stud and drywall installation in new entryway addition.
  • Continue carpet installation in student rooms and hallways.

New residence hall

  • Continue installing block walls on floor 2 and upward.
  • Continue steam line installation.