The following is an overview of work completed since June 1, 2018, and expected in the next 30 days on UW-Eau Claire construction projects.
Work completed since June 1, 2018
Garfield Avenue redevelopment
(See live video stream of project — view from Schofield Hall.)
- Continued grading, irrigation installation and landscaping of project site.
- Completed city of Eau Claire utilities removal and replacement on Garfield Avenue between Hibbard Hall and Kjer/Brewer/Zorn complex.
Karlgaard Towers south tower renovation
- Completed bathroom and lounge window installations on south side of tower.
- Completed installation of hallway lighting and smoke detectors.
- Continued plumbing fixture installations.
- Completed installing rough electrical on floor 1.
- Continued installing second of two new elevators.
- Completed tile installation in bathrooms on floors 4, 3 and 2.
- Completed steel stud installation in new entryway addition.
- Continued carpet installation in student rooms and hallways.
- Started landscaping work on south side of tower.
New residence hall
(See live video streams of project — views from Karlgaard Towers, heating plant, Horan Hall.)
- Completed installing block walls on floor 2.
- Installed precast concrete floors on floor 3.
- Completed steam line installation.
- Installed chiller line for new residence hall, Governors Hall.
- Began work on electrical and plumbing piping.
Pablo Center at the Confluence
- See newest updates on the Pablo Center's website.
Work to be completed in next 30 days
Garfield Avenue redevelopment
- Continue grading, irrigation installation and landscaping of project site.
- Widen roadway and replace curb in turn area at end of Roosevelt Ave.
- Install utility tie-ins to Zorn/Brewer/Kjer.
Karlgaard Towers south tower renovation
- Plumbing fixture installations.
- Installation of penthouse doors.
- Installation of tile in bathrooms on floor 1.
- Drywall installation in new entryway addition.
- Rough electrical and plumbing work in new entryway addition.
- Carpet installation in student rooms and hallways on floors 2 and 1.
- Final painting on floors 5 through 2.
- Stone veneer installation on fireplaces in new entryway addition.
- Continue landscaping work on south side of tower.
Karlgaard Towers north tower renovation
- Begin demolition starting with 10th floor
New residence hall
- Install block walls on floors 3 and 4.
- Install precast concrete floors on floors 4 and 5.
- Continue work on electrical and plumbing piping.
Pablo Center at the Confluence
- See newest updates on the Pablo Center's website.