UW-Eau Claire construction update: Sept. 1, 2018

| Glen Mabie (video)

The following is an overview of work completed since Aug. 1, 2018, and expected in the next 30 days on UW-Eau Claire construction projects.

Above, see drone video of progress on the Garfield Avenue redevelopment project as of Aug. 30, 2018.

Work completed since Aug. 1, 2018

Garfield Avenue redevelopment

(See live video stream of project — view from Schofield Hall.)

  • Continued grading, irrigation installation and landscaping of project site.
  • Final layer of asphalt in turn area at end of Roosevelt Avenue.
  • Concrete work in corridor between Hibbard Hall and Zorn/Brewer/Kjer complex.
  • Brick pavers installation in corridor between Hibbard Hall and Zorn/Brewer/Kjer complex.
  • Continued handrail installation along sidewalk next to river.
  • Gate installation at base of Garfield Avenue hill.

Marilyn Karlgaard Hall renovation

  • First-floor plumbing fixture installations.
  • Landscaping on south side of tower.
  • New roof installation.
  • Carpet installation first-floor lobby area.
  • New furniture moved into student rooms.
  • Painted penthouse exterior.
  • Wi-Fi lock installations on student room doors.
  • Stone veneer installation on new entryway exterior.
  • Skylight installation in new entryway.

David Karlgaard Hall renovation

  • Began asbestos abatement on floors 10 and 9.
  • Demolition of bathrooms/center section on floor 10, began on 9 and 8.
  • Continued removing exterior brick façade where new lounge windows will be installed.

New residence hall

(See live video streams of project — views from heating plant and Horan Hall.)

  • Installed block walls on floor 4.
  • Started installing precast concrete floors on floor 5.
  • Continued work on electrical and plumbing piping.
  • Completed resurfacing of Governors parking lot needed following utility tie-in installation.
  • Continued installing steel studs on lower floors.

Pablo Center at the Confluence

See newest updates on the Pablo Center's website.

Work to be completed in next 30 days

Garfield Avenue redevelopment

  • Complete final landscaping.
  • Remove construction fencing as landscaping is completed.
  • Complete handrail installation along sidewalk next to river.

Marilyn Karlgaard Hall renovation

  • Install blinds in all rooms.

David Karlgaard Hall renovation

  • Continue asbestos abatement on floors 10 and 9, begin on floors 8 and 7.
  • Continue demolition of bathrooms/center section on floor 10.
  • Continue removing exterior brick façade where new lounge windows will be installed.

New residence hall

  • Install block walls on floors 5 and 6.
  • Install precast concrete floors on floors 5 and 6.
  • Continue work on electrical and plumbing piping.
  • Continue installing steel studs on lower floors.

Pablo Center at the Confluence

See newest updates on the Pablo Center's website.