The following is an overview of work completed since Dec. 1, 2018, and expected in the next 60 days on UW-Eau Claire construction projects.
Work completed since Dec. 1, 2018
David Karlgaard Hall renovation
- Asbestos abatement on remaining floors.
- Demolition of bathrooms/center section on all floors.
- Mechanical, electrical and plumbing rough-ins on floors 6 through 3.
- Masonry construction of bathroom walls on floors 6 through 3.
- Drywall installation on floors 10 through 4.
- Painting on floors 10 through 3.
New residence hall
- Roof construction.
- Drywall installation on floors 3 and 4.
- Electrical and plumbing rough-ins through floor 5.
- Interior painting on floors 2 and 3.
- Steel studs installation.
- Exterior brick installation on building's west side.
Work to be completed in next 60 days
David Karlgaard Hall renovation
- Complete mechanical, electrical and plumbing rough-ins on floor 2 and basement.
- Complete masonry construction of bathroom walls on floor 2.
- Complete drywall installation on floors 3 through 1.
- Complete painting on floors 2 and 1.
- Install ceramic tile on floors 10 through 4.
- Complete study lounge window installations on floors 10 through 2.
- Complete exterior metal panels installation on floors 10 through 2.
New residence hall
- Complete drywall installation on floors 5 and 6.
- Complete electrical and plumbing rough-ins on floor 6.
- Complete interior painting through floor 4.
- Complete exterior brick installation on building's east and south sides.
- Begin installing windows and exterior metal panels.