The following is an overview of work completed since Oct. 1, 2018, and expected in the next 60 days on UW-Eau Claire construction projects.
Work completed since Oct. 1, 2018
David Karlgaard Hall renovation
- New windows installation.
- Asbestos abatement completed on floors 6 through 3.
- Demolition of bathrooms/center section on floors 8 through 4.
- Continued exterior brick façade removal where new lounge windows will be installed (finished through floor 5).
- Drywall installation started beginning on floor 10.
- Masonry construction of bathroom walls completed on floors 10 through 7.
- Mechanical, electrical and plumbing rough-ins completed on floors 10 through 7.
New residence hall
- Completed block wall construction on all floors.
- Installed stairwells.
- Completed precast concrete floors on all levels.
- Completed electrical rough-ins on floors 1 and 2, began on floor 3.
- Completed plumbing rough-ins on floors 1 through 3, began on floors 4 and 5.
- Continued installing steel studs through floor 5.
- Installed drywall on floors 1 and 2.
- Began roof construction.
- Began exterior brick installation on building's northwest corner and around entryways.
Work to be completed in next 60 days
David Karlgaard Hall renovation
- Complete asbestos abatement on remaining floors.
- Complete demolition of bathrooms/center section on all floors.
- Complete mechanical, electrical and plumbing rough-ins on floors 6 through 3.
- Complete masonry construction of bathroom walls on floors 6 through 3.
- Complete drywall installation on floors 10 through 6.
New residence hall
- Complete roof construction.
- Complete drywall installation on floors 3 through 5.
- Complete electrical and plumbing rough-ins through floor 6.
- Begin interior painting.
- Complete steel studs installation.
- Continue exterior brick installation on building's west side.