----- Monday, September 01, 2008 -----
USITT First Meeting Next Fall
6:00 PM-7:00 PM (Green Room)
When: Monday, September 01, 2008 6:00 PM-7:00 PM. Central Standard Time
Where: Green Room
*~*~*~*~*~*~*~*~*~*
----- Tuesday, September 02, 2008 -----
Bent - Production Meeting
All Day (HFA 169)
Scenic Plans and Final Props List and Research Due
Lunacy - Production Meeting
All Day (HFA 169)
Research Presentations Meeting
Maine - Production Meeting
All Day (HFA 169)
Initial Production Meeting
Theatre Open House
6:30 PM-8:30 PM (Riverside Theatre)
----- Wednesday, September 03, 2008 -----
Bent Auditions
All Day (Kjer Theatre)
----- Thursday, September 04, 2008 -----
Bent Callbacks
All Day (Kjer Theatre)
----- Monday, September 08, 2008 -----
Bent - Production Meeting
All Day (HFA 169)
Build Begins
Lunacy - Production Meeting
All Day (HFA 169)
Working GP and Section
----- Monday, September 15, 2008 -----
Bent - Production Meeting
All Day (HFA 169)
Paint Elevations Due
Maine - Production Meeting
All Day (HFA 169)
Research Presentation Meeting
----- Monday, September 22, 2008 -----
Bent - Production Meeting
All Day (HFA 169)
Lunacy - Production Meeting
All Day (HFA 169)
Final GP and Sketch or Model Due
Bent - Designer Run Thru
6:00 PM-10:00 PM (HFA 169)
----- Thursday, September 25, 2008 -----
Bent - Hang and Focus
6:00 PM-10:00 PM (Kjer Theatre) (every day from 6:00 PM to 10:00 PM)
----- Friday, September 26, 2008 -----
Bent - Hang and Focus
6:00 PM-10:00 PM (Kjer Theatre) (every day from 6:00 PM to 10:00 PM)
----- Saturday, September 27, 2008 -----
Bent - Focus
9:00 AM-1:00 PM (Kjer Theatre)
Bent - Focus
2:00 PM-6:00 PM (Kjer Theatre)
----- Monday, September 29, 2008 -----
Bent - Paint Week
September 29-October 3 (Kjer Theatre)
Bent - Production Meeting
All Day (HFA 169)
Lunacy - Production Meeting
All Day (HFA 169)
Scenic Plans Due and Final Props List and Research
Maine - Production Meeting
All Day (HFA 169)
Working GP and Section